Thanks for the extra information.
We've made a change to address this for tomorrow's builds, dated November 2 and later.
Announcement
Collapse
No announcement yet.
X
-
I put up 2 pictures from which it can be seen that initially the Calendar Event had a duration of 7 days, and after dragging it has a duration of 6 days. And the end time of the event changed from 0:59 to 23:59
Leave a comment:
-
hi Hirn ,
We tried your sample and things seem to be working as expected - but you didn't mention what error you're seeing!
Please describe what issue you're having, perhaps showing a screenshot if that will help.
thanks
Isomorphic Support
Leave a comment:
-
Timeline drag CalendarEvent bug
I have encountered an error calculating the end date in a Calendar Event when dragging an event.
I also give an example of the code. I have only slightly modified the example from https://smartclient.com/smartgwt/sho...imple_timeline
In order for the error to manifest itself, you need to drag the Event so that the beginning of the event falls on 10/28/2022.
TestBug.java TimelineData.java TimelineLaneData.java
SmartClient Ajax RIA system
Version v12.1p_2022-10-30/Pro Deployment (2022-10-30)
Last edited by Hirn; 31 Oct 2022, 05:25.Tags: None
Leave a comment: