SmartClient Version: SNAPSHOT_v11.1d_2017-01-17/AllModules Development Only (built 2017-01-17)
Hello, it seems that when you've got 3 events in day view, say A, B, C, where A and C are consecutive (non overlapping) and B overlaps both of them, if you drag (or resize) a fourth event (say D), so it has same duration and same start time as C, the canvas of event D will cover that of event C.
The developer console doesn't show errors.
I hope this video helps:
https://www.youtube.com/watch?v=ppmhvL-AOgI
Hello, it seems that when you've got 3 events in day view, say A, B, C, where A and C are consecutive (non overlapping) and B overlaps both of them, if you drag (or resize) a fourth event (say D), so it has same duration and same start time as C, the canvas of event D will cover that of event C.
The developer console doesn't show errors.
I hope this video helps:
https://www.youtube.com/watch?v=ppmhvL-AOgI
Comment