Hi,
I am using the new functionality to show lanes in the dayview. One thing is that different lanes (resources) can have different working day start and ends.
I see that the getWorkdayStart and getWorkdayEnd only get the date as a parameter, so not the lane.
Is there a way to compute/set the workdaystart and end by resource/lane?
gr. Martin
I am using the new functionality to show lanes in the dayview. One thing is that different lanes (resources) can have different working day start and ends.
I see that the getWorkdayStart and getWorkdayEnd only get the date as a parameter, so not the lane.
Is there a way to compute/set the workdaystart and end by resource/lane?
gr. Martin
Comment